Projects

Hinesville Treatment Facility #2

Hinesville, Georgia

Construction of a 2.0 MGD Wastewater Treatment Facility with Sequencing Batch Reactors and Disc Filters. All new construction, including sitework and access road. Additionally, the construction of an additional 2.0 MGD SBR structure.

City of Hinesville

P.C. Simonton & Associates

$13,600,043

June 15, 2006

November 1, 2008

Twelve Mile Creek WWTP Expansion

Union County, North Carolina

Construction of a new headworks/screening system with odor control, new influent pumps and drives, two carrousel oxidation ditches, two secondary clarifiers, effluent filtration, UV disinfection, RAS/WAS pump station, sludge stabilization system, standby generators, electrical systems, instrumentation, and related site work and piping.

Union County

Hazen and Sawyer

$20,717,620

March 2008

Generostee Creek WWTP Expansion

Anderson, South Carolina

Major expansion of an existing wastewater treatment plant involving the addition of a 3.8 MGD treatment train, which will increase the plant capacity to 10 MGD. Construction of a primary clarifier, first stage trickling filter, intermediate clarifier, second stage trickling filter, final clarifier, recirculation/sludge pump building, chlorine contact tanks, digester complex with two new digesters and a digester pump room, magnesium hydroxide feed building, Roll-off container building, generators, instrumentation and controls, related process piping and equipment, and site work as well as an upgrade to some of the existing equipment, modifications to existing facilities, and instrumentation and controls.

City of Anderson

Design South Professionals, Inc.

$16,300,000

November 15, 2004

December 1, 2006