Projects

Richland Creek Trunk Sewer Replacement

Greenville, South Carolina

Replacement of 15,000 LF of ductile iron pipe ranging from 24" to 42" in diameter. Four major jack and bore crossings, several creek crossings, blasting, major bypass pumping of existing sewer mains.

Renewable Water Resources

Brown and Caldwell

$12,684,179

September 22, 2016

February 2018

Highway 41 Water Main Phase IV

Cobb County, Georgia

Installation of approximately 15,700 lineal feet of Ductile Iron Pipe. Average depth of the pipe was 15 feet. Work was performed mostly In a 4 lane GDOT highway. Project also included a hand-mined 84" tunnel.

Cobb County Marietta Water Authority

Atkins

$13,655,964

July 2015

April 2017

Rivermeade Force Main Improvements

Atlanta, Georgia

This project consisted of replacement of 2,400 LF of 8" sewer force-mains. This replacement was accomplished using pneumatic pipe bursting. In addition, there were four external point repairs, one manhole replacement, and re-configuring of the piping at the pump station.

City of Atlanta

City of Atlanta

$757,272

October 30, 2015

December 7, 2015