Terrell Creek Trunk Sewer Replacement

Atlanta, Georgia

This project comprised of upsizing select portions of sewer lines in the City of Atlanta. The work included Bypass Pumping, Pre and Post CCTV Inspection, replacing existing pipe using conventional open cut, pipe-bursting, and jack and bore methods. Project also included rehabilitation, replacement and installation of sewer manholes.

• 10,274 LF of 36" pipe
• 395 LF of 48" Jack & Bores
• 59 Precast Concrete Manholes
• Grout fill abandonment of existing sewer

City of Atlanta

City of Atlanta

$13,449,542

January 31, 2019

July 31, 2020

Howell Mill Road Sewer Outfall

Atlanta, Georgia

This contract comprises the emergency repair of sanitary and storm sewers in The project will consist of the realignment and construction of roughly 1,500 linear feet of 10-Inch diameter force main and the Installation of a new duplex pump station.

The methods of construction will consist of utilizing both traditional open-cut / replacement and trenchless methods, with the ultimate goal of eliminating sewer overflows, ensure the long-term structural stability of the sewer, Improve water quality, and protect the public health and safety of the ratepayers.

The new pump station will be design-build.

City of Atlanta

City of Atlanta

$4,009,183

January 1, 2019

June 30, 2019

Dekalb County Gravity Sewer System Rehab

Dekalb County, Georgia

The Project includes rehabilitation and replacement assignments at nineteen locations within DeKalb County. Work assignments include assessment using CCTV, cured-in-place pipe lining, pipe and/or manhole point repairs, pipe replacements utilizing either open-cut or pipe-bursting methods, and manhole rehabilitation and/or replacement.

The Project will be implemented in two phases:

Phase One: Design and GMP Development Services

Phase Two: Final Design and Construction Services (Component 1)
• Includes roughly 23,020 lf of assessment using CCTV
• 18 ea point repairs
• 5,282 lf of CIPP lining
• 25,004 lf of pipe replacement
• Pipe sizes ranging from 8”-24” diameter

This project is utilizing the design-build (D-B) delivery method.

Dekalb County

Brown and Caldwell

$11,811,473

September 15, 2017

May 20, 2020